In a competitive environment requiring ever more control, our teams supported our customer to ensure the traceability and compliance of nuclear power plant parts.
TECHNICAL ENVIRONMENT
Machining, assembly, welding and inspection of parts for nuclear power plants
Dematerialisation of documentation, transferred to SAP
ACHIEVEMENTS
Vérification des dossiers de fabrication
Vérification des procès-verbaux de contrôle
Vérification des gestes SAP
Formation des contrôleurs aux nouveaux outils informatiques
CASE 2 – DESIGN
Client
For one of the world’s leading turbine design companies
CHALLENGES
Ensuring that work is carried out perfectly in accordance with customer requirements.
TECHNICAL ENVIRONMENT
Hydroelectric power plant
Closed-loop control, automation, fluid mechanics
AutoCAD
ACHIEVEMENTS
Our consulting engineers served as guarantors of the design of speed control systems for international hydroelectric power plant projects.
They studied the potential replacement of mechanical controllers with digital controllers (compliance with specifications, electrical engineering work, sizing, project management).
CASE 3 – CONSTRUCTION SITE MANAGEMENT
Client
German wind turbine manufacturer.
CHALLENGES
Ensuring that work is carried out perfectly in accordance with customer requirements.
TECHNICAL ENVIRONMENT
Renewable energies
Wind turbine installation work
MS Project, AutoCAD,
SAP (project systems)
ACHIEVEMENTS
Creation of 15 wind farms – 96 wind turbines for a total cost ≥ €225 million
Our consulting engineers were in charge of overall supervision in terms of deadlines, quality and costs for phases ranging from preparation to final works acceptance.